Job calculator

Deck footing calculator

Enter the length of the beam and how far apart the posts go. Footing size and depth are under Advanced; use your local frost depth.

Measurements

Example values. Replace them with yours.

Read as 16 ft 0 in

ft-in

Example: 8 ft 0 in

ft-in

Type it the way the tape reads: 10' 6-1/2", 126" or 3.2 m.

Buy list

Beam 16 ft 0 in long, posts 8 ft 0 in apart

  1. 18
    bags80 lb concrete mixFor 3 footings, 12 in across, 4 ft 0 in deep.
  2. 3
    form tubes12 in across, cut to 4 ft 0 in or more
  3. 3
    post basesto suit your posts
  4. 3
    postscut to your deck height

Estimate only, not engineering advice. Values marked Example are not recommendations: adjust them to your local building code, permit requirements and the products you buy.

The working

  1. Posts per beam16 ft ÷ 8 ft, rounded up, + 1 = 3
  2. Footings3 × 1 beam = 3 footings
  3. Concrete: hole areaπ × 6 in × 6 in = 113.1 sq in
  4. Concrete: volume of 3 holes3 × 113.1 sq in × 48 in ÷ 1728 = 9.42 cu ft
  5. Concrete: add 10% waste9.42 cu ft × 1.1 = 10.37 cu ft
  6. Concrete: cubic yards10.37 cu ft ÷ 27 = 0.384 → 0.39 cu yd
  7. Concrete: bags, rounded up10.37 cu ft ÷ 0.6 cu ft per bag = 17.28 → 18 bags

Assumptions and sources

FigureUsedSourcePulled
Footing depthAt least 12 in below the ground, and below the frost line where there is one.1 ft 0 in at leastAmerican Wood Council, DCA 6: Prescriptive Residential Wood Deck Construction Guide, 2015 IRC version (April 2018)2026-11-17
Post spacingSet by your beam size and span. Not sized here.8 ft 0 inExample value, change it above as per design requirements.
Footing diameterSet by the load and your soil. Not sized here.12 inExample value, change it under Advanced as per design requirements.
Footing depthUse your local frost depth.4 ft 0 inExample value, change it under Advanced as per design requirements.
Yield of one 80 lb bag0.6 cu ftQUIKRETE Concrete Mix No. 1101 data sheet, revised October 20222026-11-16
Waste allowanceCovers waste, over-excavation and other contingencies.10% used. Published range 4% to 10%NRMCA Concrete in Practice CIP 8, Discrepancies in Yield2026-11-16