Job calculator
Deck footing calculator
Enter the length of the beam and how far apart the posts go. Footing size and depth are under Advanced; use your local frost depth.
Measurements
Example values. Replace them with yours.
Read as 16 ft 0 in
ft-in
Example: 8 ft 0 in
ft-in
Type it the way the tape reads: 10' 6-1/2", 126" or 3.2 m.
Buy list
Beam 16 ft 0 in long, posts 8 ft 0 in apart
- 18bags80 lb concrete mixFor 3 footings, 12 in across, 4 ft 0 in deep.
- 3form tubes12 in across, cut to 4 ft 0 in or more
- 3post basesto suit your posts
- 3postscut to your deck height
Estimate only, not engineering advice. Values marked Example are not recommendations: adjust them to your local building code, permit requirements and the products you buy.
The working
- Posts per beam16 ft ÷ 8 ft, rounded up, + 1 = 3
- Footings3 × 1 beam = 3 footings
- Concrete: hole areaπ × 6 in × 6 in = 113.1 sq in
- Concrete: volume of 3 holes3 × 113.1 sq in × 48 in ÷ 1728 = 9.42 cu ft
- Concrete: add 10% waste9.42 cu ft × 1.1 = 10.37 cu ft
- Concrete: cubic yards10.37 cu ft ÷ 27 = 0.384 → 0.39 cu yd
- Concrete: bags, rounded up10.37 cu ft ÷ 0.6 cu ft per bag = 17.28 → 18 bags
Assumptions and sources
| Figure | Used | Source | Pulled |
|---|---|---|---|
| Footing depthAt least 12 in below the ground, and below the frost line where there is one. | 1 ft 0 in at least | American Wood Council, DCA 6: Prescriptive Residential Wood Deck Construction Guide, 2015 IRC version (April 2018) | 2026-11-17 |
| Post spacingSet by your beam size and span. Not sized here. | 8 ft 0 in | Example value, change it above as per design requirements. | |
| Footing diameterSet by the load and your soil. Not sized here. | 12 in | Example value, change it under Advanced as per design requirements. | |
| Footing depthUse your local frost depth. | 4 ft 0 in | Example value, change it under Advanced as per design requirements. | |
| Yield of one 80 lb bag | 0.6 cu ft | QUIKRETE Concrete Mix No. 1101 data sheet, revised October 2022 | 2026-11-16 |
| Waste allowanceCovers waste, over-excavation and other contingencies. | 10% used. Published range 4% to 10% | NRMCA Concrete in Practice CIP 8, Discrepancies in Yield | 2026-11-16 |