Job calculator
Wood fence calculator
Enter the length and height of the fence. Post spacing, rails, picket width and nails are under Advanced. Post holes follow the concrete maker’s own rule.
Measurements
Example values. Replace them with yours.
Read as 50 ft 0 in
ft-in
Read as 6 ft 0 in
ft-in
Type it the way the tape reads: 10' 6-1/2", 126" or 3.2 m.
Buy list
50 ft 0 in fence, 6 ft 0 in high
- 8posts3-1/2 in square, at least 9 ft 0 in long
- 21railsat least 8 ft 0 in long
- 110pickets5-1/2 in wide, 6 ft 0 in long
- 23bags80 lb concrete mixFor 8 posts, holes 10-1/2 in across and 3 ft 6 in deep.
- 5bags50 lb all-purpose gravel6 in under each post.
- 660nailsor screws, for the pickets
Estimate only, not engineering advice. Values marked Example are not recommendations: adjust them to your local building code, permit requirements and the products you buy.
The working
- Sections, rounded up50 ft ÷ 8 ft per section = 6.25 → 7 sections
- Posts7 sections + 1 = 8 posts
- Rails7 sections × 3 = 21 rails
- Pickets, rounded up600 in ÷ 5.5 in per picket = 109.09 → 110 pickets
- Nails110 pickets × 3 rails × 2 = 660 nails
- Post length6 ft above ground × 1.5 = 9 ft, a third of it in the ground
- Hole across3 × 3.5 in = 10.5 in
- Hole depth9 ft ÷ 3 + 6 in of gravel = 3.5 ft
- Concrete: hole areaπ × 5.25 in × 5.25 in = 86.59 sq in
- Concrete: less the post86.59 sq in − 3.5 in × 3.5 in = 74.34 sq in
- Concrete: volume of 8 holes8 × 74.34 sq in × 36 in ÷ 1728 = 12.39 cu ft
- Concrete: add 10% waste12.39 cu ft × 1.1 = 13.63 cu ft
- Concrete: cubic yards13.63 cu ft ÷ 27 = 0.505 → 0.51 cu yd
- Concrete: bags, rounded up13.63 cu ft ÷ 0.6 cu ft per bag = 22.72 → 23 bags
- Gravel under the postsπ × 5.25 in × 5.25 in × 6 in × 8 = 2.41 cu ft
- Gravel bags, rounded up2.41 cu ft ÷ 0.5 cu ft per bag = 4.81 → 5 bags
Assumptions and sources
| Figure | Used | Source | Pulled |
|---|---|---|---|
| Post spacing | 8 ft 0 in | Example value, change it under Advanced as per design requirements. | |
| Rails per section | 3 | Example value, change it under Advanced as per design requirements. | |
| Picket widthA 6 in board, dressed. | 5-1/2 in | Western Red Cedar Lumber Association (Real Cedar), Fence specifications | 2026-11-17 |
| Nails per picket at each rail | 2 | Example value, change it under Advanced as per design requirements. | |
| Post width | 3-1/2 in | Example value, change it under Advanced as per design requirements. | |
| Post holeThree times the post width across; a third of the post in the ground, plus 6 in of gravel. | 10-1/2 in across, 3 ft 6 in deep | QUIKRETE project sheet, Setting Posts | 2026-11-17 |
| Yield of one 80 lb bag | 0.6 cu ft | QUIKRETE Concrete Mix No. 1101 data sheet, revised October 2022 | 2026-11-16 |
| Waste allowanceCovers waste, over-excavation and other contingencies. | 10% used. Published range 4% to 10% | NRMCA Concrete in Practice CIP 8, Discrepancies in Yield | 2026-11-16 |
| Yield of one 50 lb gravel bag | 0.5 cu ft | Do it Best listing for QUIKRETE 0.5 Cu. Ft. 50 Lb. All-Purpose Gravel | 2026-11-17 |